Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 760
Message text: Activity & has not been assigned capacity requirements
You want to mainatin employee assignments to an activity.
There are no capacity requirements for the activity.
No employees can be assigned.
Choose another activity. If necessary maintain the work center of the
activity involved and/or schedule the network, to produce capacity
requirements.
Error message extract from SAP system. Copyright SAP SE.
CN760
- Activity & has not been assigned capacity requirements ?The SAP error message CN760 indicates that a specific activity in a project (or network) does not have any capacity requirements assigned to it. This can occur in various scenarios, particularly in project management and production planning modules where activities are linked to resources and capacities.
Cause:
- Missing Capacity Requirements: The activity in question has not been assigned any capacity requirements, which means that the system does not know what resources (e.g., labor, machines) are needed to complete the activity.
- Incorrect Configuration: The configuration of the activity or the project may not be set up correctly, leading to the absence of capacity requirements.
- Data Entry Errors: There may have been an oversight during data entry, where the capacity requirements were not specified for the activity.
- Activity Type Settings: The activity type may not be configured to require capacity planning, or it may not be linked to the correct resource.
Solution:
Assign Capacity Requirements:
- Go to the activity in the project or network and check the settings.
- Ensure that the capacity requirements are defined for the activity. This can typically be done in the activity details where you can specify the required resources and their quantities.
Check Activity Type Configuration:
- Review the configuration of the activity type in the system. Ensure that it is set up to allow capacity planning and that it is linked to the appropriate resources.
Review Project Settings:
- Check the overall project settings to ensure that capacity planning is enabled and that the activities are correctly linked to the project structure.
Data Validation:
- Validate the data entered for the activity to ensure that all necessary fields are filled out correctly, including any resource assignments.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on capacity planning and activity management in your version of SAP.
Related Information:
CJ20N
(Project Builder) or CN22
(Change Network) to access and modify project or network activities.By following these steps, you should be able to resolve the CN760 error and ensure that your activities are properly assigned capacity requirements.
Get instant SAP help. Start your 7-day free trial now.
CN759
Invalid account assignment category -> check your settings
What causes this issue? You want to assign an account assignement category to a component. This account assignment type has not been maintained.How t...
CN758
No more item numbers available (please check)
What causes this issue? The item number for components in the network can no longer be assigned automatically, since the number interval has been exh...
CN761
Enter currency. Cannot execute unit costing
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN762
Long text for activity & could not be copied
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.