Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 686
Message text: Delivery date for a purchase requisition is unrealistic -> see log
You have scheduled a network.
The delivery date for at least one purchase requisition is unrealistic.
In order to keep this delivery date, the purchase requisition would
have to be released in the past. The release date can be today at the
earliest.
Call up the scheduling log and check the dates of the relevant
components and their activities.
Error message extract from SAP system. Copyright SAP SE.
CN686
- Delivery date for a purchase requisition is unrealistic -> see log ?The SAP error message CN686 indicates that the delivery date specified for a purchase requisition is considered unrealistic. This can occur for various reasons, such as the delivery date being too far in the future, not aligning with the production schedule, or being outside of acceptable lead times.
Causes:
- Lead Time Issues: The delivery date may not account for the necessary lead time required for procurement or production.
- Calendar Settings: The delivery date may fall on a non-working day or outside of the defined working calendar.
- Material Availability: The material may not be available for the requested delivery date due to stock levels or production schedules.
- Incorrect Date Entry: The date may have been entered incorrectly, either manually or through a system error.
- Vendor Constraints: The vendor may have limitations on delivery dates based on their own production or shipping schedules.
Solutions:
- Review and Adjust Delivery Date: Check the delivery date in the purchase requisition and adjust it to a more realistic timeframe based on lead times and vendor capabilities.
- Check Material Master Data: Ensure that the material master data is correctly set up, including lead times and availability checks.
- Consult the Log: The error message suggests checking the log for more details. This log can provide insights into why the date is considered unrealistic.
- Verify Vendor Information: Confirm with the vendor regarding their delivery capabilities and adjust the requisition accordingly.
- Update Working Calendar: Ensure that the working calendar is correctly configured to reflect non-working days and holidays.
- Use Planning Tools: Utilize SAP planning tools to forecast and plan for material requirements more accurately.
Related Information:
By addressing the underlying causes and following the suggested solutions, you should be able to resolve the CN686 error and proceed with your procurement processes.
Get instant SAP help. Start your 7-day free trial now.
CN685
Network & was not released -> see log
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN684
Activity & was not released -> see log
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN687
Delivery date: Previous working day is the &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN688
The purchasing data is incomplete
What causes this issue? You want to allocate an externally procurred component but have not maintained all the data necessary for purchasing. Purchas...
Click on this link to search all SAP messages.