Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 492
Message text: Work for activity & element & is too large - check
When you multiple using the execution factor for work in activity &V1&
gives you a value which is too large for activity element &V2&.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
Enter a lower value for the execution factor in activity.
Error message extract from SAP system. Copyright SAP SE.
CN492
- Work for activity & element & is too large - check ?The SAP error message CN492 indicates that the work for a specific activity and element is too large. This typically occurs in the context of project management and controlling, particularly when dealing with work breakdown structures (WBS) and network activities in SAP.
Cause: Exceeding Limits: The error usually arises when the planned work (in hours or units) for an activity exceeds the maximum allowable limit set in the system. This limit can be defined in the configuration settings of the project system. Data Entry Errors: It may also occur due to incorrect data entry, where the planned work has been mistakenly entered as a very high value. System Configuration: The system may have specific configurations that restrict the amount of work that can be assigned to an activity or element.
Solution: Check Configuration Settings: Review the configuration settings in the project system to determine if there are any limits set for the maximum allowable work for
Get instant SAP help. Sign up for our Free Essentials Plan.
CN491
Duration for activity & is too large - check
What causes this issue? When you multiply with the execution factor for duration in activity &V1&, you get a value which is too large.System ...
CN490
Work for activity & is too large - check
What causes this issue? When you multiply using the execution factor for work in activity &V1&, you get a value which is too large.System Res...
CN493
Quantity of component & is too large - check
What causes this issue? When you multiply using the execution factor in the activity, you get a value for material component &V1& which is to...
CN494
Quantity in activity & is too large - check
What causes this issue? When you multiply using the execution factor in activity &V1&, you get a value for the activity quantity, which is to...