Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 487
Message text: The exection factor in the network has been reduced from & to 1
The quantity you entered in the network would lead to an execution
factor of &V1&.
The execution factor cannot exceed 999.
The system sets the execution factor in the network header to 1.
Check the quantity structure of the network.
Error message extract from SAP system. Copyright SAP SE.
CN487
- The exection factor in the network has been reduced from & to 1 ?The SAP error message CN487 indicates that the execution factor in a network has been reduced from a certain value (represented by
&
) to 1. This typically occurs in the context of project management and network scheduling within SAP's Project System (PS) module.Cause:
The execution factor is a parameter that influences the scheduling and execution of activities within a project network. The reduction of the execution factor to 1 usually indicates that the system has determined that the activity can only be executed at a normal rate, possibly due to constraints such as:
- Resource Availability: There may not be enough resources (e.g., labor, machinery) available to execute the task at the originally planned rate.
- Scheduling Conflicts: Other activities may be scheduled at the same time, leading to a bottleneck.
- Changes in Project Plan: Adjustments in the project plan or network structure may have necessitated a change in the execution factor.
- Manual Adjustments: A user may have manually adjusted the execution factor for specific reasons.
Solution:
To resolve the CN487 error, consider the following steps:
Check Resource Availability: Ensure that the necessary resources are available for the activity. If resources are limited, consider reallocating or adding more resources.
Review Network and Activity Dependencies: Examine the network structure and dependencies between activities. Look for any scheduling conflicts that may be causing the execution factor to be reduced.
Adjust Execution Factor: If appropriate, you can manually adjust the execution factor back to a higher value, provided that the resources and scheduling allow for it.
Analyze Project Changes: If there have been recent changes to the project plan, review those changes to understand their impact on the execution factor.
Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing execution factors and network scheduling.
Engage with Project Management: If the issue persists, it may be beneficial to engage with project management or a SAP consultant to analyze the situation in detail.
Related Information:
CN21
(Create Network), CN22
(Change Network), or CN41
(Network Overview) to manage networks and activities.By following these steps, you should be able to identify the cause of the CN487 error and implement a suitable solution.
Get instant SAP help. Start your 7-day free trial now.
CN486
BAdI NETW_USER_FIELDS_F4 inactive: There is no user-defined F4 help
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN484
Calculation key & not valid
What causes this issue? You are using a calculation key which is not permitted.System Response The network activity is not saved.How to fix this err...
CN488
Costs of activity & element & are becoming too large - please check
What causes this issue? If the system multipies the execution factor in activity &V1& by the costs in activity element &V2&, the prod...
CN489
Activity & element & is taking too much time - please check
What causes this issue? If the system multipies the execution factor in activity &V1& by the duration in activity element &V2&, the p...
Click on this link to search all SAP messages.