Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 372
Message text: Element & not yet finally confirmed
The control key for activity element &V1& determines that it requires a
confirmation. You must confirm the activity element before you can
close it.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Confirm activity element &V1&.
Error message extract from SAP system. Copyright SAP SE.
CN372
- Element & not yet finally confirmed ?The SAP error message CN372 ("Element & not yet finally confirmed") typically occurs in the context of project management and controlling, particularly when dealing with network activities in SAP Project System (PS). This error indicates that a certain element (like a network activity or a project element) has not been finally confirmed, which is necessary for certain operations to proceed.
Cause:
- Incomplete Confirmation: The element in question has been partially confirmed, but not all necessary confirmations have been completed.
- Status Issues: The status of the project element may not allow for final confirmation due to various reasons, such as being in a locked state or having pending transactions.
- Missing Data: Required data or prerequisites for final confirmation may be missing or not properly set up.
Solution:
- Check Confirmation Status: Review the confirmation status of the element. You can do this by navigating to the relevant transaction (e.g., CN41 for network activities) and checking the confirmation details.
- Complete Confirmations: If the element has been partially confirmed, ensure that all necessary confirmations are completed. This may involve entering additional confirmation data or processing pending confirmations.
- Review Project Settings: Ensure that the project settings allow for final confirmations. Check if there are any restrictions or settings that need to be adjusted.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on the confirmation process for the type of element you are working with.
- Check for Locks: Ensure that there are no locks on the project or network that would prevent final confirmation. This can be checked in transaction codes like SM12 (for lock entries).
- Contact Support: If the issue persists, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.
Related Information:
By following these steps, you should be able to resolve the CN372 error and successfully confirm the project element in question.
Get instant SAP help. Sign up for our Free Essentials Plan.
CN371
Activity & not yet finally confirmed
What causes this issue? The control key for activity &V1& determines that it requires a confirmation. You must confirm the activity before yo...
CN370
Network is released. Purchase requisition can no longer be changed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN373
Act. or element & must be confirmed but is only partially confirmed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN374
Subnetwork & for activity & not marked for deletion
What causes this issue? You can only set a deletion flag for activity &V2&, once you have set the deletion flag for subnetwork &V1&.S...