Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 347
Message text: Plant &1 is not assigned to the project controlling area &2
Plant &V1& is not assigned to the same controlling area (&V2&) as the
project.
INCLUDE 'NA_ALLG_ORGELEM' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Enter another plant for the network.
INCLUDE 'NA_ALLG_VORGEHEN' OBJECT DOKU ID TX
In Customizing check the assignment of organization data and change
them.
Error message extract from SAP system. Copyright SAP SE.
CN347
- Plant &1 is not assigned to the project controlling area &2 ?The SAP error message CN347 indicates that a specific plant (denoted as &1) is not assigned to the project controlling area (denoted as &2). This error typically arises when you are trying to create or manage a project in SAP Project System (PS) and the system cannot find a valid assignment between the plant and the controlling area.
Cause:
- Missing Assignment: The plant you are trying to use in the project is not assigned to the controlling area in the system.
- Incorrect Configuration: There may be a configuration issue where the plant is not properly set up in relation to the controlling area.
- Data Entry Error: There might be a mistake in the project or plant data entry, leading to the mismatch.
Solution:
To resolve the CN347 error, follow these steps:
Check Plant Assignment:
- Go to the SAP transaction code
OX19
(or navigate through the menu: SPRO > Enterprise Structure > Assignment > Logistics - General > Assign Plant to Company Code).- Verify if the plant is assigned to the correct company code and controlling area.
Assign Plant to Controlling Area:
- If the plant is not assigned, you need to assign it to the controlling area. This can be done in the same configuration area where you checked the assignment.
- Ensure that the plant is linked to the appropriate controlling area.
Review Project Settings:
- Check the project settings in transaction
CJ20N
(Project Builder) orCJ01
(Create Project) to ensure that the correct plant and controlling area are being used.Consult with Configuration Team:
- If you do not have the necessary permissions to make changes, consult with your SAP configuration team or system administrator to ensure that the plant and controlling area assignments are correct.
Testing:
- After making the necessary changes, try to recreate or modify the project to see if the error persists.
Related Information:
OX19
: Assign Plant to Company CodeCJ20N
: Project BuilderCJ01
: Create ProjectBy following these steps, you should be able to resolve the CN347 error and successfully manage your projects in SAP.
Get instant SAP help. Start your 7-day free trial now.
CN346
The event is not assigned a position in any group
What causes this issue? You want to schedule events according to their position in the sequence and relative offset. However, the event that you sele...
CN345
A negative planned independent requirement is not permitted. Check entry
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN348
Function is only possible for external activities/activity elements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN349
Supply source determination carried out for &1 / &2
What causes this issue? You added a component to be externally procured.System Response Due to the parameterization of component data the system car...