Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 269
Message text: WBS element & does not have valuated stock
You want to change the assignment of a component to a WBS element.
However, as opposed to the original WBS element, the WBS element that
you entered does not have an indivdual stock assigned.
INCLUDE NA_ALLG_NOVERARBEITUNG OBJECT DOKU ID TX
Assign the component to a WBS element that is assigned an individual
stock.
Error message extract from SAP system. Copyright SAP SE.
CN269
- WBS element & does not have valuated stock ?The SAP error message CN269 indicates that a Work Breakdown Structure (WBS) element does not have valuated stock. This typically occurs in the context of project management and controlling within SAP, particularly when dealing with project-related costs and inventory management.
Cause:
- WBS Element Configuration: The WBS element may not be properly configured to allow for valuated stock. This can happen if the WBS element is not linked to a relevant cost center or if it is not set up to track inventory.
- Stock Valuation: The stock associated with the WBS element may not be valuated. This can occur if the stock is not properly assigned to the WBS element or if the valuation method is not set up correctly.
- Project Settings: The project settings may not allow for the tracking of stock or inventory against the WBS element.
- Material Master Data: The material associated with the WBS element may not have the necessary valuation settings in the material master data.
Solution:
- Check WBS Element Configuration: Ensure that the WBS element is correctly configured to allow for valuated stock. This includes checking the settings in the project definition and ensuring it is linked to the appropriate cost center.
- Review Stock Valuation: Verify that the stock is properly valuated. You can do this by checking the material master data and ensuring that the valuation class and valuation type are correctly set.
- Adjust Project Settings: If necessary, adjust the project settings to allow for stock tracking against the WBS element. This may involve changing the project type or settings in the project profile.
- Material Master Data: Check the material master data for the materials associated with the WBS element. Ensure that the valuation type and valuation class are set correctly to allow for valuated stock.
- Transaction Codes: Use transaction codes like
CJ20N
(Project Builder) to review and adjust the WBS element settings, andMM03
(Display Material) to check the material master data.Related Information:
CJ01
(Create Work Breakdown Structure), CJ02
(Change Work Breakdown Structure), and CJ03
(Display Work Breakdown Structure).If the issue persists after checking these areas, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in project systems and inventory management.
Get instant SAP help. Start your 7-day free trial now.
CN268
Planned independent requirements not found for &1 on &2
What causes this issue? You have changed the requirements date for a planned independent requirement for material &v1&.System Response The s...
CN267
Network & has been unlocked
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN270
The component has not been allocated to valuated individual stock
What causes this issue? Unit costing is only possible for material components that have been allocated to valuated individual stocks.Error message ex...
CN271
Component allocations to individual stock still exist
What causes this issue? You want to delete the assignment of a network header or an activity to a WBS element or a sales order item. However ther are...
Click on this link to search all SAP messages.