Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 241
Message text: Network &1: Increment &2 is not possible after activity number &3
The largest activity number in network &v1& is &v3&. The increment for
acttivity numbersthat was enterd in the
<DS:SIMG.SIMG_CFMENUOLPROPS4>network profile</> can, as a result, no
longer be adhered to.
All remaining activity numbers starting at 0001 are used with increment
of 1.
Error message extract from SAP system. Copyright SAP SE.
CN241
- Network &1: Increment &2 is not possible after activity number &3 ?The SAP error message CN241 typically occurs in the context of project management and network planning within the SAP system, particularly when dealing with network activities in the Project System (PS) module. This error indicates that there is an issue with the increment of a network activity, which is not possible due to certain constraints or conditions.
Cause:
The error message CN241 can be triggered by several factors, including:
Incorrect Activity Sequence: The increment you are trying to apply may not be valid based on the current sequence of activities in the network. For example, if you are trying to increment an activity that is not in the correct order or is dependent on another activity that has not been completed.
Status of Activities: The status of the activities involved may prevent the increment. If the preceding activity is not completed or is in a status that does not allow further increments, this error will occur.
Network Configuration: There may be configuration settings in the network that restrict certain increments or changes based on the project structure or dependencies.
Resource Constraints: If there are resource constraints or if the resources assigned to the activity are not available, this can also lead to this error.
Solution:
To resolve the CN241 error, you can take the following steps:
Check Activity Sequence: Review the sequence of activities in the network. Ensure that the activity you are trying to increment is in the correct order and that all preceding activities are completed.
Review Activity Status: Check the status of the activities involved. Make sure that the preceding activities are set to a status that allows for increments. If necessary, change the status of the activities to allow for the increment.
Examine Network Configuration: Look into the network configuration settings to ensure that there are no restrictions on increments for the specific activities you are working with.
Resource Availability: Verify that the resources assigned to the activity are available and that there are no conflicts that would prevent the increment.
Consult Documentation: If the issue persists, consult SAP documentation or reach out to your SAP support team for further assistance. They may provide insights specific to your configuration or version of SAP.
Related Information:
CN21
(Create Network), CN22
(Change Network), and CN24
(Display Network) to manage network activities.By following these steps, you should be able to identify the cause of the CN241 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
CN240
The plant cannot be changed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN239
The network type cannot be changed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN242
For network &1 all 9999 operation numbers have already been assigned
What causes this issue? All the activity number from 0001 to 9999 have been used in network &v1&.System Response It is not possible to creat...
CN243
Enter a project
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.