How To Fix CN051 - Control key not available for costs


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CN - Meldungen für Netzpläne

  • Message number: 051

  • Message text: Control key not available for costs

  • Show details Hide details
  • What causes this issue?

    The control key does not exist for the general costs activity or there
    has been no indicator maintained for costs.

    System Response

    INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX

    How to fix this error?

    Check to make sure that you have entered the correct key for costs.
    INCLUDE 'NA_ALLG_VORGEHEN' OBJECT DOKU ID TX
    Make sure that the control key has been correctly defined. If necessary,
    define an indicator for costs.

    <DS:TRAN.OP67>Execute function</>
    ENDIF

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CN051 - Control key not available for costs ?

    The SAP error message CN051 ("Control key not available for costs") typically occurs in the context of project management or controlling when you are trying to post costs to a project or internal order, and the control key associated with the operation or activity is not set up correctly or is missing.

    Cause:

    1. Missing Control Key: The control key that you are trying to use for the operation or activity is not defined in the system.
    2. Incorrect Configuration: The control key may not be assigned to the relevant order type or project type.
    3. Inactive Control Key: The control key might be inactive or not allowed for cost postings.
    4. Authorization Issues: The user may not have the necessary authorizations to use the control key.

    Solution:

    1. Check Control Key Configuration:

      • Go to the transaction code OPKP (for controlling) or OPL8 (for project management) to check the configuration of control keys.
      • Ensure that the control key you are trying to use is defined and active.
    2. Assign Control Key to Order Type:

      • Ensure that the control key is assigned to the relevant order type or project type in the configuration settings.
    3. Review Control Key Settings:

      • Check the settings of the control key to ensure it allows for cost postings. You can do this in the configuration settings for controlling.
    4. Check User Authorizations:

      • Verify that the user has the necessary authorizations to use the control key. This can be checked in the user roles and profiles.
    5. Use a Different Control Key:

      • If the control key is not available or not suitable, consider using a different control key that is configured correctly for cost postings.

    Related Information:

    • Transaction Codes:

      • OPKP: Control Key Configuration
      • OPL8: Project Management Control Key Configuration
      • CJ20N: Project Builder (to check project settings)
    • Documentation: Refer to SAP Help documentation for detailed information on control keys and their configuration.

    • SAP Notes: Check for any relevant SAP Notes that might address specific issues related to control keys and costs.

    • Testing: After making changes, perform a test posting to ensure that the error is resolved.

    By following these steps, you should be able to identify the cause of the CN051 error and implement a solution to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant