Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 048
Message text: The status of the network '&' does not permit changes
You want to change the network but the network has one of the folowing
statuses:
<LS>locked</>
<ls>technically completed</>
Therefore the network cannot be changed.
INCLUDE NA_ALLG_NOFUNKTION OBJECT DOKU ID TX
Cancel the status, if possible
Error message extract from SAP system. Copyright SAP SE.
CN048
- The status of the network '&' does not permit changes ?The SAP error message CN048 indicates that the status of a network in the Project System (PS) does not allow for changes to be made. This typically occurs when the network is in a status that restricts modifications, such as "TECO" (Technically Completed), "CLSD" (Closed), or other statuses that indicate the network is no longer active for changes.
Causes:
Network Status: The network may be in a status that prohibits changes. Common statuses that prevent changes include:
- TECO (Technically Completed)
- CLSD (Closed)
- Other statuses defined in the system that restrict modifications.
Authorization Issues: The user may not have the necessary authorizations to make changes to the network.
System Configuration: The system may be configured to restrict changes to networks based on certain criteria or business rules.
Solutions:
Check Network Status:
- Navigate to the network in question and check its current status. If it is in a status like TECO or CLSD, you will need to reverse this status if changes are necessary.
- You can use transaction code CN22 to change the status of the network if you have the necessary permissions.
Reopen the Network:
- If the network is technically completed (TECO), you may need to set it back to a status that allows changes. This can be done using transaction CN22 to change the status back to "In Process" or another appropriate status.
Authorization Check:
- Ensure that you have the necessary authorizations to make changes to the network. If not, contact your SAP security administrator to request the required permissions.
Consult with Project Management:
- If the network is closed or completed, consult with the project management team to determine if changes are necessary and if they can approve reopening the network.
Review Configuration:
- If the issue persists, review the configuration settings in the Project System to ensure that the status management is set up correctly according to your organization’s policies.
Related Information:
Transaction Codes:
Documentation: Refer to SAP Help documentation for detailed information on network statuses and their implications in the Project System.
SAP Notes: Check for any relevant SAP Notes that may address specific issues related to network status and changes.
By following these steps, you should be able to resolve the CN048 error and make the necessary changes to the network.
Get instant SAP help. Start your 7-day free trial now.
CN047
Control key of superior activity is not changed
What causes this issue? The subnetwork assignment was deleted. If the control key of the superior activity was changed when creating a subnetwork, th...
CN046
Control key "&" from network profile "&" is copied
What causes this issue? The subnetwork assignment was deleted. If the control key of the superior activity &V3&/&V4& was changed when...
CN049
------ Error messages for organization elements -------------------------
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN050
Control key not available for external processing
What causes this issue? The control key has either not been defined or no indicator has been maintained for external processing.System Response INCL...
Click on this link to search all SAP messages.