Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 028
Message text: Activities are not within time frame of WBS elements
The activity dates do not lie within the basic dates of the WBS element.
You cannot save.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Adjust the dates accordingly.
Error message extract from SAP system. Copyright SAP SE.
CN028
- Activities are not within time frame of WBS elements ?The SAP error message CN028 ("Activities are not within time frame of WBS elements") typically occurs when you are trying to assign activities to a Work Breakdown Structure (WBS) element, but the dates of the activities do not fall within the start and finish dates of the WBS element. This can happen in project management scenarios where the scheduling of tasks is critical.
Cause:
- Date Mismatch: The start or finish date of the activity is outside the defined time frame of the WBS element.
- WBS Element Dates: The WBS element may have been defined with specific start and end dates that do not encompass the activity dates.
- Project Structure Changes: Changes in the project structure or timeline may have led to discrepancies between the WBS and the activities.
- Incorrect Activity Dates: The dates entered for the activity may be incorrect or not aligned with the project plan.
Solution:
- Check Activity Dates: Review the start and finish dates of the activity you are trying to assign. Ensure they fall within the time frame of the WBS element.
- Adjust WBS Dates: If the activity dates are correct and need to be retained, consider adjusting the start and finish dates of the WBS element to include the activity dates.
- Reassess Project Plan: If there are multiple activities or WBS elements involved, reassess the overall project plan to ensure that all components are aligned.
- Use Transaction Codes: Use transaction codes like
CJ20N
(Project Builder) to view and modify the WBS elements and their associated activities.- Consult with Project Manager: If you are unsure about the changes, consult with the project manager or the person responsible for project planning to ensure that any adjustments are appropriate.
Related Information:
By addressing the date discrepancies and ensuring alignment between activities and WBS elements, you can resolve the CN028 error and proceed with your project management tasks in SAP.
Get instant SAP help. Start your 7-day free trial now.
CN027
Enter an activity number
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN026
No elements for activity & exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN029
Log contains no entries
What causes this issue? No errors were found when checking whether the activity dates lie within the basic dates of the WBS element.System Response ...
CN030
You cannot assign to activity "&"
What causes this issue? You cannot assign a production order or maintenance order to an activity. You must assign the production or maintenance order...
Click on this link to search all SAP messages.