How To Fix CMT076 - Enter a future Baseline date


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CMT - CM: Message Class in CM Environment

  • Message number: 076

  • Message text: Enter a future Baseline date

  • Show details Hide details
  • What causes this issue?

    You want to create a Baseline for a specific target date. However, you
    have not entered a date, or the date you have entered is in the past.

    System Response

    The system expects you to enter a date in the future.

    How to fix this error?

    Enter a date in the field <LS>Baseline date</> that lies in the future.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CMT076 - Enter a future Baseline date ?

    The SAP error message CMT076, which states "Enter a future Baseline date," typically occurs in the context of project management or project system modules within SAP. This error indicates that the baseline date you are trying to enter is either in the past or is not valid for the operation you are attempting to perform.

    Cause:

    1. Past Date Entry: The baseline date you are trying to set is earlier than the current date.
    2. Incorrect Context: The operation you are performing may require a baseline date that is specifically set in the future.
    3. System Configuration: There may be specific configurations or settings in your SAP system that enforce this rule.

    Solution:

    1. Enter a Future Date: Ensure that the baseline date you are entering is a date that is in the future. You can do this by selecting a date that is after the current date.
    2. Check Project Status: If you are working within a project, ensure that the project is in a status that allows for the setting of a baseline date.
    3. Review Documentation: Consult the project management documentation or guidelines within your organization to understand the requirements for setting baseline dates.
    4. Consult with SAP Support: If you are unsure about the correct date to enter or if the error persists despite entering a future date, consider reaching out to your SAP support team for assistance.

    Related Information:

    • Baseline Dates: In project management, a baseline date is used to establish a reference point for measuring project performance. It is crucial for tracking progress and managing timelines.
    • SAP Modules: This error is commonly encountered in modules such as SAP Project System (PS) or SAP Controlling (CO).
    • User Permissions: Ensure that you have the necessary permissions to set or modify baseline dates in the system.

    By following these steps, you should be able to resolve the CMT076 error and successfully enter a valid baseline date.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant