Message type: E = Error
Message class: CK - Product Costing Messages
Message number: 259
Message text: Material & in plant & has no alternative BOM & and usage &
You are attempting to cost with alternative BOM &V3& BOM usage &V4&,
but this alternative BOM does not exist for material &v1& in plant
&v2&. You entered the combination of the alternative BOM and the BOM
usage in the initial screen of the cost estimate, or you maintained it
in the costing view of the material master.
Enter a valid alternative BOM and BOM usage.
Error message extract from SAP system. Copyright SAP SE.
CK259
- Material & in plant & has no alternative BOM & and usage & ?The SAP error message CK259 indicates that a material in a specific plant does not have an alternative Bill of Materials (BOM) for the specified usage. This error typically arises during the process of material costing or when trying to create a production order, as the system requires a valid BOM to determine the components needed for production.
Cause:
- Missing Alternative BOM: The material in question does not have an alternative BOM defined for the specified usage in the plant.
- Incorrect BOM Usage: The BOM usage specified in the transaction does not match any existing BOM for the material.
- Plant-Specific Configuration: The BOM may exist for another plant but not for the one specified in the transaction.
- Data Inconsistency: There may be inconsistencies in the master data or BOM configuration.
Solution:
Check BOM Configuration:
- Go to the BOM transaction (CS01, CS02, or CS03) and check if an alternative BOM exists for the material in the specified plant and usage.
- If it does not exist, you may need to create a new alternative BOM using CS01.
Create Alternative BOM:
- If the alternative BOM is missing, create it by using the transaction CS01. Ensure you specify the correct material, plant, and usage.
Verify BOM Usage:
- Ensure that the BOM usage you are trying to access is correct. Common usages include production (usage 1), engineering (usage 2), etc. Make sure you are using the correct one.
Check Plant Assignment:
- Verify that the BOM is assigned to the correct plant. If the BOM exists for another plant, you may need to copy it to the desired plant.
Consult Documentation:
- Review SAP documentation or help files for further details on BOM management and alternative BOMs.
Data Consistency Check:
- Run consistency checks on your master data to ensure there are no discrepancies that could lead to this error.
Related Information:
By following these steps, you should be able to resolve the CK259 error and ensure that the necessary BOMs are in place for your materials.
Get instant SAP help. Sign up for our Free Essentials Plan.
CK258
Material & in plant & has no alternative BOM &
What causes this issue? You are attempting to cost with <DS:GLOS.alternative_BOM>alternative BOM</> &V3&. Either this alternative...
CK257
Cost element missing from BOM item with purchase price
What causes this issue? In the BOM item for material &V1& a procurement price was maintained but no cost element was provided. The item is p...
CK260
Additive costs cannot be updated
What causes this issue? No cost element is assigned to cost component structure &V1&, cost component &V2&, chart of accounts &V3&...
CK261
Errors occurred when costs were calculated (see log)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.