Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 512
Message text: Actual finish date for WBS element & cannot be maintained
You cannot enter any actual finish dates for WBS element &V1& if
the subordinate WBS element does not have an actual finish date
or the activities in the WBS element do not all have final confirmations
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Enter the actual dates for the subordinate WBS elements.
Error message extract from SAP system. Copyright SAP SE.
CJ512
- Actual finish date for WBS element & cannot be maintained ?The SAP error message CJ512 indicates that the actual finish date for a Work Breakdown Structure (WBS) element cannot be maintained. This typically occurs when there are certain conditions or settings in the project management module that prevent changes to the actual finish date.
Causes of Error CJ512
Project Status: The project or WBS element may be in a status that does not allow changes. For example, if the project is closed or completed, you may not be able to modify the actual finish date.
Period Locking: The posting period for the project may be closed. If the period in which the actual finish date falls is locked, you will not be able to make changes.
Authorizations: The user may not have the necessary authorizations to change the actual finish date for the WBS element.
Dependencies: There may be dependencies or constraints set on the WBS element that prevent changes to the actual finish date.
Data Consistency: There may be inconsistencies in the data related to the project or WBS element that need to be resolved before changes can be made.
Solutions to Error CJ512
Check Project Status: Verify the status of the project or WBS element. If it is closed or completed, you may need to reopen it or adjust the status to allow changes.
Open Posting Period: Ensure that the posting period is open. You can check this in the financial settings and, if necessary, open the period for posting.
Review Authorizations: Check the user roles and authorizations to ensure that the user has the necessary permissions to make changes to the WBS element.
Examine Dependencies: Look for any dependencies or constraints that may be affecting the ability to change the actual finish date. Resolve any issues that may be present.
Data Consistency Check: Run a consistency check on the project data to identify and resolve any inconsistencies that may be preventing changes.
Consult Documentation: Refer to SAP documentation or consult with your SAP support team for specific guidance related to your system configuration.
Related Information
By following these steps, you should be able to identify the cause of the CJ512 error and implement the appropriate solution.
Get instant SAP help. Start your 7-day free trial now.
CJ511
Network & locked. Time scheduling not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ510
Network & locked. You cannot shift dates
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ513
No dates exist for WBS element &
What causes this issue? You have entered an object in WBS scheduling that does not have a start or finish date.System Response INCLUDE 'NA_ALLG...
CJ514
No overlapping dates found
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.