Message text: Activities for WBS element & could not be read
The activities for WBS element &V1& can not be read in the project
planning board because they are currently being edited by another user.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
RESET N1
Select the menu options <LS>Extras -> Log -> Lock log - activity</>.
You will receive a log which shows the users and the activities they
are editing (that is, locking).
Error message extract from SAP system. Copyright SAP SE.
CJ471
- Activities for WBS element & could not be read ?The SAP error message CJ471 indicates that activities for a specific Work Breakdown Structure (WBS) element could not be read. This error typically arises in the context of project management within SAP, particularly when dealing with project planning and controlling.
Cause:
- WBS Element Not Defined: The WBS element you are trying to access may not be defined in the system or may have been deleted.
- Authorization Issues: The user may not have the necessary authorizations to view or access the activities associated with the WBS element.
- Data Inconsistency: There may be inconsistencies in the data, such as missing or incomplete entries in the project structure.
- Project Status: The project or WBS element may be in a status that does not allow for the reading of activities (e.g., locked or archived).
- Technical Issues: There could be technical issues with the SAP system, such as database problems or system configuration errors.
Solution:
- Check WBS Element: Verify that the WBS element exists and is correctly defined in the system. You can do this by navigating to the WBS element in the project structure.
- Review Authorizations: Ensure that the user has the necessary authorizations to access the WBS element and its activities. This may involve checking user roles and permissions.
- Data Consistency Check: Run consistency checks on the project data to identify and resolve any inconsistencies. This can often be done through transaction codes like CJEN (Project Structure) or using the Project System (PS) tools.
- Project Status Review: Check the status of the project and the WBS element. If it is locked or archived, you may need to unlock it or change its status to allow access.
- Technical Support: If the issue persists, consider reaching out to your SAP Basis or technical support team to investigate any underlying system issues.
Related Information:
By following these steps, you should be able to diagnose and resolve the CJ471 error in SAP.
Get instant SAP help. Start your 7-day free trial now.
CJ470
====================== Project planning board ===========================
What causes this issue? There is no WBS element for standard WBS element &V1&. The program terminated.System Response INCLUDE 'NA_ALLG_...
CJ469
You cannot move the root element of the hierarchy
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ472
Enter profile for project planning board in project profile "&"
What causes this issue? You have not defined a profile for the project planning board in project profile &V1&.System Response INCLUDE '...
CJ473
Scheduled dates cannot be changed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...