Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 266
Message text: WBS element & is inactive. Function not possible
You want to change a WBS element in a simulation version that is
inactive.
&DEPENDENCIES&
The simulation versions that you are editing only contians a subtree of
a project. When you transfer a subtree to a simulation version, the
superior WBS elements are also transfered. However, this is only for
reference purposes; they are only displayed and cannot be changed.
INCLUDE NA_ALLG_NOVERARBEITUNG OBJECT DOKU ID TX
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
CJ266
- WBS element & is inactive. Function not possible ?The SAP error message CJ266 indicates that a Work Breakdown Structure (WBS) element is inactive, which means that you cannot perform certain functions or transactions related to that WBS element. This error typically arises in project management scenarios within SAP, particularly when dealing with project structures and financial transactions.
Cause:
- Inactive WBS Element: The primary cause of this error is that the WBS element you are trying to use has been marked as inactive. This can happen if the project has been completed, closed, or if the WBS element was manually set to inactive.
- Project Status: The overall project status may also affect the status of its WBS elements. If the project is in a status that does not allow further transactions, the WBS elements will inherit this status.
- Authorization Issues: Sometimes, the user may not have the necessary authorizations to activate or work with the WBS element.
Solution:
Activate the WBS Element:
- If you have the necessary permissions, you can activate the WBS element. This can typically be done in the Project System (PS) module by navigating to the WBS element in question and changing its status to active.
- Use transaction code CJ02 (Change WBS Element) to modify the status.
Check Project Status:
- Ensure that the overall project is not in a closed or completed status. If the project is closed, you may need to reopen it or create a new project for further transactions.
- Use transaction code CJ20N (Project Builder) to check the project and its WBS elements.
Review Authorizations:
- If you do not have the necessary permissions to activate the WBS element, contact your SAP security administrator to review and adjust your authorizations.
Consult Documentation:
- Review the project documentation or consult with your project manager to understand the status and intended use of the WBS element.
Related Information:
By following these steps, you should be able to resolve the CJ266 error and continue working with the relevant WBS elements in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
CJ265
Project &1 version &2 is being changed (sub-tree &3)
What causes this issue? The sub-tree &v3& of project &v1& version &v2& is being changed in the database in the background.Err...
CJ264
Project &1 version &2 is being changed
What causes this issue? Project &v1& version &V2& is being changed in the background in the database.Error message extract from SAP s...
CJ267
Enter a version name
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ268
Enter a user status
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...