Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 203
Message text: Cannot set finish date
You cannot set a finish date, because not all subordinate WBS elements
have a finish date and/or not all of the corresponding activities have
been finally confirmed.
INCLUDE NA_ALLG_NOVERARBEITUNG OBJECT DOKU ID TX
Finally confirm all the assigned activities and/or set a final date for
all subordinate WBS elements.
Error message extract from SAP system. Copyright SAP SE.
CJ203
- Cannot set finish date ?The SAP error message CJ203 "Cannot set finish date" typically occurs in the context of project management within SAP, particularly when dealing with project definitions, work breakdown structures (WBS), or network activities. This error indicates that there is an issue with the scheduling of a project or activity, preventing the system from allowing the user to set a finish date.
Causes of CJ203 Error
Inconsistent Dates: The start and finish dates of the project or activity may be inconsistent. For example, the finish date cannot be earlier than the start date.
Dependencies: There may be dependencies or constraints set on the project or activity that prevent the finish date from being changed.
Status of the Project: The project or activity may be in a status that does not allow changes to the dates (e.g., completed or closed).
Resource Availability: If resources assigned to the project are not available during the proposed finish date, the system may prevent the change.
Scheduling Parameters: The scheduling parameters or settings in the project may not allow for the proposed finish date due to various constraints.
Solutions to CJ203 Error
Check Dates: Ensure that the finish date you are trying to set is later than the start date. Adjust the dates accordingly.
Review Dependencies: Check for any dependencies or constraints that may be affecting the scheduling of the project or activity. You may need to adjust or remove these dependencies.
Project Status: Verify the status of the project or activity. If it is completed or closed, you may need to reopen it or change its status to allow for date modifications.
Resource Allocation: Review the resource allocation for the project. Ensure that the resources are available for the new finish date. If not, consider adjusting the resource assignments.
Scheduling Settings: Review the scheduling settings in the project. Ensure that there are no constraints that would prevent the finish date from being set.
Use Transaction Codes: Utilize relevant transaction codes (like CJ20N for project management) to navigate to the project and make necessary adjustments.
Related Information
Transaction Codes: Familiarize yourself with transaction codes related to project management, such as CJ20N (Project Builder), CJ02 (Change Project), and CJ03 (Display Project).
SAP Notes: Check SAP Notes for any known issues or patches related to the CJ203 error. SAP frequently updates its system, and there may be specific notes addressing this error.
Documentation: Refer to SAP documentation or help files for detailed information on project management and scheduling functionalities.
Consult with SAP Support: If the issue persists after trying the above solutions, consider reaching out to SAP support for further assistance.
By following these steps, you should be able to identify the cause of the CJ203 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
CJ202
Processing only possible in the Project System
What causes this issue? You cannot use the functions of statistical investment projects for projects and WBS elements which were created or changed i...
CJ201
Entry & missing for screen sequence control
What causes this issue? An internal error has occurred. Your entry is not in the Table TC10. The system issues an error message and will not allow y...
CJ204
No maintenance orders available
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CNV_10940_MSG540
Error while updating data in control system
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.