Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 175
Message text: The dates for WBS element & cannot be changed
You cannot change the dates of WBS element &v1&.
Possible reasons for this are:
1.) You do not have the necessary authorization
2.) You have only selected a sub-hierarchy of the corresponding
project.
Case 1
INCLUDE NA_ALLG_BERECHTIGUNG OBJECT DOKU ID TX
Case 2:
Select the whole project. To do so mainatin the project definition in
initial screen.
Error message extract from SAP system. Copyright SAP SE.
The SAP error message CJ175 indicates that the dates for a Work Breakdown Structure (WBS) element cannot be changed. This typically occurs when there are constraints or settings in the system that prevent modifications to the dates of the WBS element. Here are some common causes, potential solutions, and related information for this error:
Causes:
Status of the WBS Element: The WBS element may be in a status that does not allow date changes. For example, if the WBS is locked or has been set to a status that restricts changes (like "Completed" or "Closed"), you will not be able to modify the dates.
Dependencies: There may be dependencies or relationships with other WBS elements or activities that prevent changes to the dates. If the WBS element is linked to other elements that have already been scheduled, changing the dates may not be allowed.
Project Planning Settings: The project planning settings may restrict changes to certain fields, including dates, based on the project type or configuration.
Authorizations: The user may not have the necessary authorizations to change the dates of the WBS element.
Locked Periods: If the fiscal period is locked in the system, it may prevent changes to the WBS element's dates.
Solutions:
Check WBS Status: Review the status of the WBS element. If it is in a status that restricts changes, you may need to change the status to allow for modifications.
Review Dependencies: Check for any dependencies or relationships with other WBS elements or activities. If there are linked elements, you may need to adjust those first.
Project Settings: Consult with your project manager or SAP administrator to review the project settings and see if there are any restrictions in place that need to be modified.
Authorization Check: Ensure that you have the necessary authorizations to make changes to the WBS element. If not, contact your system administrator to request the required permissions.
Unlock Periods: If the fiscal period is locked, you may need to unlock it or wait until it is open for changes.
Use Transaction CJ02: If you are trying to change the WBS element, use transaction CJ02 (Change WBS Element) and ensure you are following the correct procedures.
Related Information:
If the issue persists after trying the above solutions, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in project systems.
Get instant SAP help. Start your 7-day free trial now.
Feature | Free Access | Free Trial |
---|---|---|
Basic SAP error explanation | ![]() |
![]() |
Step-by-Step Usage Guide | ![]() |
![]() |
Interactive SAP Coach Assistance | ![]() |
![]() |
AI Troubleshooting for T-Code Errors | ![]() |
![]() |
CJ174 WBS element & has no activities
What causes this issue? You want to display activities for a WBS element. No ac...
CJ173 Select a valid line
Self-Explanatory Message Since SAP believes that this specific error message is ...
CJ176 Automatic cost calculation for networks was activated
Self-Explanatory Message Since SAP believes that this specific error message is ...
CJ177 Capacity calculation was activated and takes place from next scheduling
Self-Explanatory Message Since SAP believes that this specific error message is ...
SAP messages fall into 3 different categories: Error messages
(message type = E), Warnings (W) or Informational (I) messages.
An error message will prevent you from continuing your work - it is a hard stop and you need to fix the error before you can proceed. A warning message will stop your work, however, you can then bypass the warning by pressing the Enter key on your keyboard. That said, it is still good practice to investigate the cause of the warning message and address it. An information message will not stop your work and is truly just for informational purposes.
Click on this link to search all SAP messages.