Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 086
Message text: Milestone &1 is assigned to another WBS element
This milestone has already been assigned to another WBS element. The
asignment cannot be changed any more.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Delete the milestone and create a new milestone for the selected WBs
element.
Error message extract from SAP system. Copyright SAP SE.
CJ086
- Milestone &1 is assigned to another WBS element ?The SAP error message CJ086 indicates that a milestone is already assigned to another Work Breakdown Structure (WBS) element. This typically occurs when you attempt to assign a milestone to a WBS element that is already linked to a different WBS element, which is not allowed in SAP.
Cause:
- Duplicate Assignment: The milestone you are trying to assign is already linked to another WBS element.
- Incorrect WBS Element: You may be trying to assign the milestone to the wrong WBS element.
- System Configuration: There may be specific configurations or restrictions in your SAP system that prevent the assignment of milestones to multiple WBS elements.
Solution:
Check Existing Assignments:
- Use transaction code CJ20N (Project Builder) or CJ03 (Display WBS Element) to check where the milestone is currently assigned.
- Identify the WBS element that currently has the milestone assigned.
Reassign the Milestone:
- If you need to assign the milestone to a different WBS element, you will first need to remove it from the current WBS element.
- Navigate to the current WBS element and delete or disassociate the milestone.
- After removing it, you can then assign the milestone to the desired WBS element.
Consult with Project Management:
- If the milestone is critical and needs to be associated with multiple WBS elements, consult with your project management team to determine the best course of action.
Check for System Restrictions:
- If you believe the assignment should be allowed, check with your SAP administrator to see if there are any specific configurations or restrictions in place that need to be adjusted.
Related Information:
Transaction Codes:
Documentation: Refer to SAP Help documentation for more details on managing milestones and WBS elements.
User Roles: Ensure that you have the necessary permissions to make changes to WBS elements and milestones.
SAP Notes: Check for any relevant SAP Notes that might address specific issues or bugs related to milestone assignments.
By following these steps, you should be able to resolve the CJ086 error and successfully manage your milestones within the SAP system.
Get instant SAP help. Start your 7-day free trial now.
CJ085
Create an object by double-clicking or drag and drop
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ084
The activity has not been assigned to the WBS elements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ087
Error during scheduling. Save function not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ088
Final date must be later than &
What causes this issue? You have entered a date that does not lie within the planned range for scheduling.System Response The system issues an error...
Click on this link to search all SAP messages.