Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 057
Message text: No valid capacity for finite scheduling
No capacity, next to which the indicator <ZH>relevant for finite
scheduling</> has been placed, is assigned to the work center.
You should place the indicator <ZH>relevant for finite scheduling</>
next to at least one capacity.
Error message extract from SAP system. Copyright SAP SE.
C7057
- No valid capacity for finite scheduling ?The SAP error message C7057 "No valid capacity for finite scheduling" typically occurs during the scheduling process in SAP when the system cannot find available capacity to schedule a production order or a planned order. This can happen for various reasons, and understanding the cause is essential for resolving the issue.
Causes:
Capacity Constraints: The work center or production line may not have enough available capacity to accommodate the scheduled operations. This can be due to:
- Overlapping orders that consume the same resources.
- Maintenance or downtime scheduled for the work center.
- Incorrect capacity planning settings.
Incorrect Master Data: Issues with master data can lead to this error, such as:
- Incorrectly defined work centers or production resources.
- Capacity categories not set up properly.
- Incorrectly defined production versions or routing.
Scheduling Parameters: The scheduling parameters in the production order or planned order may not align with the available capacity.
Finite Scheduling Settings: If finite scheduling is enabled, the system will only schedule operations if there is sufficient capacity available. If not, it will trigger this error.
Solutions:
Check Work Center Capacity:
- Go to the work center in question and review the capacity settings. Ensure that the available capacity is sufficient for the planned production.
- Check for any maintenance or downtime that may be affecting capacity.
Review Production Orders:
- Look for overlapping production orders that may be consuming the same resources. Adjust the scheduling of these orders if necessary.
Adjust Scheduling Parameters:
- Review the scheduling parameters in the production order or planned order. Ensure they are set correctly to allow for scheduling.
Update Master Data:
- Verify that the master data for work centers, routing, and production versions is accurate and complete. Make any necessary corrections.
Use Alternative Scheduling:
- If finite scheduling is causing issues, consider switching to infinite scheduling temporarily to see if that resolves the problem. This can help identify if the issue is capacity-related.
Capacity Planning:
- Conduct a capacity planning run to identify any bottlenecks or capacity issues in the production process.
Related Information:
CM01
(Capacity Planning) or CO02
(Change Production Order) to analyze and adjust capacity settings.S_ALR_87013558
(Capacity Evaluation) to get insights into capacity utilization and availability.By following these steps, you should be able to identify the cause of the C7057 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
C7056
Capacity & not available
What causes this issue? The system could not find any remaining available capacity within the planning period.How to fix this error? Increase the pl...
C7055
Division by 0 when calculating operation quantity
What causes this issue? The system issues an error message and will not allow you to continue with this transaction until the error is resolved. Syst...
C7058
Relationships to other standard networks exist
What causes this issue? In this standard network, there are relationships to other standard networks.System Response The system ignores the relation...
C7059
Detailed scheduling level - Order &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.