Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 042
Message text: Relationship: No operating time maintained in work center for scheduling
No operating time has been maintained for the work center in the rel.
Scheduling is carried out using an operating time of 0:00 to 24:00.
Maintain an operating time in the work center.
Error message extract from SAP system. Copyright SAP SE.
C7042
- Relationship: No operating time maintained in work center for scheduling ?The SAP error message C7042, which states "Relationship: No operating time maintained in work center for scheduling," typically occurs when there is an attempt to schedule a production order or a task that requires operating times for a work center, but those times have not been defined in the work center settings.
Cause:
- Missing Operating Times: The primary cause of this error is that the work center associated with the operation does not have any operating times defined. Operating times are essential for scheduling as they determine when the work center is available for production.
- Incorrect Work Center Assignment: The work center assigned to the operation may not be the correct one, or it may not be set up properly.
- Work Center Configuration: The work center may not be fully configured, or it may be inactive.
Solution:
To resolve the C7042 error, follow these steps:
Check Work Center Configuration:
- Go to the transaction code
CR02
(Change Work Center) orCR03
(Display Work Center).- Enter the work center ID and check the details.
- Ensure that the operating times are maintained in the "Basic Data" or "Scheduling" tab.
Maintain Operating Times:
- If operating times are missing, you need to enter them. This includes defining the available capacity, shifts, and any other relevant scheduling information.
- Make sure to specify the correct time intervals for the work center.
Verify Work Center Assignment:
- Check the routing or production order to ensure that the correct work center is assigned to the operation.
- If necessary, update the routing or production order to point to the correct work center.
Check for Inactive Work Centers:
- Ensure that the work center is active. If it has been marked as inactive, it will not be considered for scheduling.
Recheck Scheduling Parameters:
- After making the necessary changes, recheck the scheduling parameters in the production order or routing to ensure they are set correctly.
Related Information:
Transaction Codes:
CR01
: Create Work CenterCR02
: Change Work CenterCR03
: Display Work CenterCA01
: Create RoutingCA02
: Change RoutingCO01
: Create Production OrderCO02
: Change Production OrderDocumentation: Refer to SAP Help documentation for detailed information on work center configuration and scheduling.
User Roles: Ensure that you have the necessary authorizations to make changes to work centers and production orders.
By following these steps, you should be able to resolve the C7042 error and successfully schedule your production orders.
Get instant SAP help. Start your 7-day free trial now.
C7041
No work center in the relationship (Operating time via calender from rel)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7040
Schedule conflict: Contradicting time constraints
What causes this issue? You have entered time contraints for the activity that have caused discrepancies in scheduling. The reasons could include: Th...
C7043
Rel: No capacity category maintained in work center for scheduling
What causes this issue? No capacity category has been maintained for scheduling in the work work center in the relationship.System Response Scheduli...
C7044
Relationship: Calendar does not exist
What causes this issue? You have maintained a calendar which is not defined in the system.System Response Scheduling is carried out using the Gregor...
Click on this link to search all SAP messages.