Message type: E = Error
Message class: C7 - Scheduling
Message number: 038
Message text: Schedule conflict: Constraint is too late
You have maintained a date constraint for the end of the activity.
Backward scheduling has determined a latest date which is before the
constraint.
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Check the date constraint of the activity.
Check the basic dates of the network in the network header.
Error message extract from SAP system. Copyright SAP SE.
C7038
- Schedule conflict: Constraint is too late ?The SAP error message C7038, "Schedule conflict: Constraint is too late," typically occurs in the context of production planning and scheduling within SAP. This error indicates that there is a scheduling conflict due to a constraint that cannot be met within the defined time frame. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- Scheduling Constraints: The error often arises when there are constraints (like resource availability, production lead times, or delivery dates) that cannot be satisfied within the planned schedule.
- Capacity Issues: If the production capacity is insufficient to meet the demand within the required time frame, this can lead to scheduling conflicts.
- Incorrect Dates: If the planned start or finish dates for production orders are set incorrectly, it may lead to conflicts with other orders or constraints.
- Dependencies: There may be dependencies between tasks or orders that are not being respected, leading to conflicts in the schedule.
Solutions:
- Review Constraints: Check the constraints set for the production order or scheduling. Ensure that they are realistic and can be met with the available resources.
- Adjust Scheduling Parameters: Modify the scheduling parameters in the production order or the planning settings to allow for more flexibility in scheduling.
- Capacity Planning: Ensure that the capacity of resources (machines, labor, etc.) is sufficient to meet the production requirements. You may need to adjust the capacity or reschedule other orders.
- Change Dates: If possible, adjust the planned start or finish dates of the production order to resolve the conflict.
- Check Dependencies: Review any dependencies between orders or tasks to ensure they are correctly defined and do not lead to conflicts.
- Use Alternative Resources: If a specific resource is causing the conflict, consider using alternative resources that may be available.
Related Information:
CO02
(Change Production Order) or CM21
(Capacity Planning) to review and adjust production orders and capacity.By addressing the underlying causes of the scheduling conflict, you can resolve the C7038 error and ensure smoother production planning and execution.
Get instant SAP help. Start your 7-day free trial now.
C7037
Schedule conflict: Constraint is too early
What causes this issue? The system has carried out forward scheduling and has calculated an earliest date either which is after the time constraint f...
C7036
Scheduled finish is after basic finish date
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7039
Cannot keep within time constraint
What causes this issue? When carrying out scheduling, the system could not keep the time constraint which you entered for the activity.System Respons...
C7040
Schedule conflict: Contradicting time constraints
What causes this issue? You have entered time contraints for the activity that have caused discrepancies in scheduling. The reasons could include: Th...
Click on this link to search all SAP messages.