Message class: C7 - Scheduling
Message number: 037
Message text: Schedule conflict: Constraint is too early
The system has carried out forward scheduling and has calculated an
earliest date
either which is after the time constraint for the start of the activity
or the activity is confirmed and has an actual start date which is
before the earliest date.
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Check the time constraint for the activity.
Check the basic dates for the network in the network header.
Error message extract from SAP system. Copyright SAP SE.
C7037
- Schedule conflict: Constraint is too early ?The SAP error message C7037, "Schedule conflict: Constraint is too early," typically occurs in the context of production planning and scheduling within SAP. This error indicates that there is a scheduling conflict due to a constraint that is set too early in the production process, which prevents the system from creating a feasible schedule.
Cause:
- Early Constraints: The error usually arises when there are constraints (like start dates, finish dates, or resource availability) that are set earlier than the available capacity or the required lead times for the production process.
- Resource Availability: If the resources (machines, labor, etc.) are not available at the time the schedule is trying to allocate them, it can lead to this error.
- Production Orders: If production orders are scheduled to start before the necessary prerequisites (like material availability or previous operations) are completed, this error can occur.
- Dependencies: There may be dependencies between tasks that are not being respected, leading to scheduling conflicts.
Solution:
- Review Constraints: Check the constraints set on the production order or scheduling. Ensure that the start and finish dates are realistic and align with resource availability.
- Adjust Scheduling Parameters: Modify the scheduling parameters in the production order or the planning settings to allow for more flexibility in scheduling.
- Check Resource Availability: Ensure that the resources required for the production are available at the scheduled time. If not, adjust the schedule accordingly.
- Review Dependencies: Make sure that all dependencies between tasks are correctly defined and that no task is scheduled to start before its prerequisites are completed.
- Use Capacity Planning Tools: Utilize SAP's capacity planning tools to analyze resource availability and adjust the production schedule based on realistic capacity.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on scheduling and constraints in your version of SAP.
Related Information:
By addressing the underlying causes of the scheduling conflict, you can resolve the C7037 error and ensure a smoother production planning process.
Get instant SAP help. Start your 7-day free trial now.
C7036
Scheduled finish is after basic finish date
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7035
Scheduled start is before basic start date
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7038
Schedule conflict: Constraint is too late
What causes this issue? You have maintained a date constraint for the end of the activity. Backward scheduling has determined a latest date which is ...
C7039
Cannot keep within time constraint
What causes this issue? When carrying out scheduling, the system could not keep the time constraint which you entered for the activity.System Respons...