How To Fix C7036 - Scheduled finish is after basic finish date


C7036 - Overview

  • Message type: E = Error

  • Message class: C7 - Scheduling

  • Message number: 036

  • Message text: Scheduled finish is after basic finish date

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message C7036 - Scheduled finish is after basic finish date ?
    The SAP error message C7036, which states "Scheduled finish is after basic finish date," typically occurs in the context of project management or production planning within SAP. This error indicates that the scheduled finish date of a task or activity exceeds the basic finish date that has been defined for that task or activity.
    
    Cause: Incorrect Scheduling: The scheduled finish date for a task has been set later than the basic finish date, which is usually defined in the project or task settings. Changes in Task Duration: If the duration of a task has been extended or if there are delays in preceding tasks, it may push the scheduled finish date beyond the basic finish date. Resource Constraints: If resources are not available as planned, it may lead to rescheduling of tasks, causing the scheduled finish to exceed the basic finish date. Manual Entry Errors: Users may have manually entered incorrect dates or durations, leading

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.