Message type: E = Error
Message class: C7 - Scheduling
Message number: 028
Message text: No work center or calender in operation/activity
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
C7028
- No work center or calender in operation/activity ?The SAP error message C7028 ("No work center or calendar in operation/activity") typically occurs in the context of production planning or project management when the system cannot find a valid work center or calendar for a specific operation or activity in a routing or task list. This can hinder the ability to schedule or execute production orders or project activities. Causes: Missing Work Center: The operation/activity in the routing does not have an assigned work center. Missing Calendar: The work center does not have an associated calendar defined, which is necessary for scheduling. Incorrect Configuration: The work center may be incorrectly configured or inactive. Routing Issues: The routing itself may be incomplete or incorrectly set up, leading to missing links to work centers. Master Data Issues: There may be issues with the master data for the work center or the routing. Solutions: Check Work Center Assignment: Go to the routing or task list in question and verify that each
Get instant SAP help. Sign up for our Free Essentials Plan.
C7027
Quantity unit of the operation/activity is invalid
What causes this issue? The quantity unit that you have maintained in the operation does not exist.System Response INCLUDE 'NA_ALLG_NOVERARBEIT...
C7026
Scheduling type not defined, scheduling type = "only capacity reqmts"
What causes this issue? The key that you have entered for the scheduling type does not exist.System Response Scheduling is carried out using the sch...
C7029
No release period key defined for scheduling
What causes this issue? You have not defined a scheduling margin key for the planned order.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG'...
C7030
Start date is in the past: today scheduling
What causes this issue? The start date determined in scheduling is in the past. In customizing, you have defined the number of days that the start da...