How To Fix C6201 - Deactivate overall network scheduling


SAP Error Message - Details

  • Message type: E = Error

  • Message class: C6 - Messages PPC orders service routines

  • Message number: 201

  • Message text: Deactivate overall network scheduling

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message C6201 - Deactivate overall network scheduling ?

    The SAP error message C6201, which states "Deactivate overall network scheduling," typically occurs in the context of project management and network scheduling within SAP's Project System (PS) module. This error indicates that the overall scheduling for a network is not activated, which can prevent the system from performing certain scheduling functions.

    Cause:

    The error can arise due to several reasons:

    1. Network Not Scheduled: The network in question has not been scheduled, which means that the system does not have the necessary data to perform overall scheduling.
    2. Settings in Project Management: The project or network settings may not allow for overall scheduling, possibly due to configuration settings in the project management module.
    3. Incomplete Data: Required data for scheduling (like activities, relationships, or resources) may be missing or incomplete.
    4. User Authorization: The user may not have the necessary authorizations to perform scheduling actions.

    Solution:

    To resolve the C6201 error, you can take the following steps:

    1. Schedule the Network:

      • Go to the network in question and ensure that it is scheduled. You can do this by using transaction code CN22 (Change Network) or CN41 (Display Network) and then selecting the option to schedule the network.
    2. Check Network Settings:

      • Verify the settings for the network in the project management configuration. Ensure that overall scheduling is enabled for the network.
    3. Complete Required Data:

      • Ensure that all necessary data for the network is complete. This includes checking that all activities, relationships, and resources are properly defined.
    4. Review Authorizations:

      • Check if the user has the necessary authorizations to perform scheduling. If not, contact your SAP security administrator to grant the required permissions.
    5. Consult Documentation:

      • Refer to SAP documentation or help files for additional guidance on network scheduling and the specific error message.
    6. SAP Notes:

      • Check the SAP Support Portal for any relevant SAP Notes that may address this specific error or provide additional troubleshooting steps.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes such as CN22, CN41, CJ20N (Project Builder), and CNO1 (Create Network).
    • SAP Help Portal: Utilize the SAP Help Portal for detailed documentation on Project System functionalities and error messages.
    • Community Forums: Engage with SAP community forums or user groups for shared experiences and solutions related to this error.

    By following these steps, you should be able to resolve the C6201 error and successfully activate overall network scheduling in your SAP system.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant