Do you have any question about this error?
Message type: E = Error
Message class: C5 - Master Recipe
Message number: 613
Message text: Lot size of production version does not match BOM alternative
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Please adapt the lot size ranges.
Error message extract from SAP system. Copyright SAP SE.
C5613
- Lot size of production version does not match BOM alternative ?The SAP error message C5613 indicates that there is a mismatch between the lot size defined in the production version and the lot size specified in the Bill of Materials (BOM) alternative. This error typically arises during the production planning or order creation process when the system checks the compatibility of the production version with the BOM alternative.
Cause:
- Lot Size Mismatch: The lot size defined in the production version does not match the lot size defined in the BOM alternative. This can happen if the production version is set up with a specific lot size that is different from what is defined in the BOM.
- Incorrect BOM Alternative: The BOM alternative being used may not be compatible with the production version due to different lot size settings.
- Configuration Issues: There may be configuration issues in the material master or production version settings that lead to this mismatch.
Solution:
Check Production Version:
- Go to the production version in the material master and verify the lot size settings. Ensure that the lot size is correctly defined and matches the expected values.
Check BOM Alternative:
- Review the BOM alternative associated with the production version. Ensure that the lot size defined in the BOM alternative matches the lot size in the production version.
- If necessary, adjust the BOM alternative to match the production version's lot size.
Adjust Lot Sizes:
- If the production version and BOM alternative need to be aligned, you may need to adjust the lot sizes in either the production version or the BOM alternative to ensure they match.
Review Material Master Settings:
- Check the material master settings for any discrepancies in the lot size definitions. Ensure that the settings are consistent across the relevant views (e.g., MRP, Work Scheduling).
Consult Documentation:
- Review SAP documentation or help resources for additional guidance on managing production versions and BOM alternatives.
Testing:
- After making adjustments, test the changes by attempting to create a production order or perform the action that previously triggered the error.
Related Information:
CS03
(Display BOM), C202
(Display Production Version), and MM03
(Display Material Master) to check the relevant settings.By following these steps, you should be able to resolve the C5613 error and ensure that your production version and BOM alternative are correctly aligned.
Get instant SAP help. Start your 7-day free trial now.
C5612
Date of production version does not match BOM alternative
What causes this issue? The validity of the production version is outside the range of validity of the BOM.System Response The system issues an erro...
C5611
This BOM alternative does not exist. It will be created
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C5614
Check BOM alternative proposal
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C5615
The "from" lot size must not exceed the "to" lot size
What causes this issue? The "to" lot size must always be greater than the "from" lot size.System Response The system issues an e...
Click on this link to search all SAP messages.