How To Fix AP198 - Next higher WBS element already has its own budget


SAP Error Message - Details

  • Message type: E = Error

  • Message class: AP - Investment program messages

  • Message number: 198

  • Message text: Next higher WBS element already has its own budget

  • Show details Hide details
  • What causes this issue?

    An appropriation request is assigned to an investment program position,
    or is to be assigned to an investment program position.
    The following settings have been made for this program position:
    Subordinate WBS element &V1& that is assigned to the appropriation
    request, and thereby indirectly assigned to the program position,
    should receive its budget solely from budget distribution from this
    program position.
    All WBS elements that are assigned thereby indirectly assigned to the
    program position, and are above WBS element &V1& in the hierarchy, as
    well as those that are above the WBS elements that are subordinate to
    WBS element &V1& (in other words, these superior WBS elements are in a
    "path" above WBS element &V1&), should also be budgeted automatically,
    meaning they can only receive budgets equaling the amount entered for
    the budget distribution. These superior WBS elements should only be
    budgeted automatically in this way, that is, they are not allowed to
    have their own, distributable budget.
    However, at least one WBS element, which is above WBS element &V1&,
    already has its own, distributable budget.

    How to fix this error?

    First reduce the existing distributable budget of the WBS element(s)
    above WBS element &V1& to zero (for example, by using budget returns).
    You can display the distributable budget in each project budgeting
    function by setting the view for "distributable."

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message AP198 - Next higher WBS element already has its own budget ?
    The SAP error message AP198 indicates that there is an issue with budget allocation in the context of Work Breakdown Structure (WBS) elements. Specifically, it means that the next higher WBS element already has its own budget, which prevents the system from allowing further budget allocations to the lower-level WBS element.
    
    Cause: Budget Constraints: The next higher WBS element has a budget that is already allocated, and the system does not allow further budget assignments to its child elements if it conflicts with the existing budget. Hierarchy Issues: The structure of the WBS may not be set up correctly, leading to conflicts in budget assignments. Budgeting Control Settings: The budgeting control settings in the system may restrict the allocation of budgets to lower-level WBS elements if the parent already has a budget.
    Solution: Review Budget Allocation: Check the budget assigned to the next higher WBS element. If it is fully allocated, you may need to adjust

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant