Do you have any question about this error?
Message type: E = Error
Message class: 7A - PS Progress Analysis
Message number: 330
Message text: Network activity is assigned to an account header - note long text
You are processing a network activity or activity element assigned to a
header. Because cost information is stored on the network header, the
system cannot determine any earned values for this operation.
You can continue processing.
Use networks assigned to an operation to calculate earned values. To
enable an aggregation of the percentage of completion, choose either
'work' or a 'manual weight' within the progress version as the basis
for weighting.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
7A330
- Network activity is assigned to an account header - note long text ?The SAP error message 7A330 indicates that there is network activity assigned to an account header, which is not allowed. This typically occurs in the context of project management or network planning within SAP, particularly in modules like SAP Project System (PS) or SAP Controlling (CO).
Cause:
The error arises when you attempt to perform an operation (like posting costs or assigning resources) on a network activity that is incorrectly linked to an account header. In SAP, account headers are used to summarize costs or revenues, and network activities should be assigned to specific cost elements or accounts rather than to headers.
Solution:
To resolve this error, you can take the following steps:
Check Network Activity Assignment:
- Go to the relevant transaction (e.g., CJ20N for project management).
- Review the network activities and ensure that they are correctly assigned to the appropriate cost elements or accounts, not to account headers.
Adjust the Assignment:
- If you find that a network activity is incorrectly assigned to an account header, you will need to reassign it to the correct cost element or account.
- This can typically be done in the network activity details or through the relevant configuration settings.
Review Configuration Settings:
- Ensure that your project system and controlling settings are correctly configured to prevent such assignments in the future.
- Check the settings for account assignment categories and ensure they align with your business processes.
Consult Documentation:
- Refer to SAP documentation or help files for more detailed guidance on managing network activities and account assignments.
Seek Help from SAP Support:
- If the issue persists or if you are unsure about making changes, consider reaching out to your SAP support team or consulting with SAP directly for assistance.
Related Information:
By following these steps, you should be able to identify the root cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
7A329
Cost element group & does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
7A328
Create an activity for network &1 and activity element &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
7A333
Different names in different controlling areas
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
7A334
Statistical key figure &1 does not exist in controlling area &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.