Do you have any question about this error?
Message type: E = Error
Message class: 61 - Fehlermeldungen fuer Bedarfsplanung
Message number: 263
Message text: Missing configuration in planned order &1
Planned orders for a configurable material must have a configuration
valuation.
If this does not exist, an error occurs.
The BOM for this planned order cannot be exploded which causes a
termination when planning the material in MRP.
Determine the cause of the error and correct it.
Delete the incorrect planned order and then repeat the planning run for
the material.
Error message extract from SAP system. Copyright SAP SE.
61263
- Missing configuration in planned order &1 ?The SAP error message "61263 Missing configuration in planned order &1" typically occurs in the context of production planning and material requirements planning (MRP) when there is a planned order that lacks the necessary configuration data. This can happen in scenarios where configurable materials are involved, and the system cannot find the required configuration for the planned order.
Cause:
- Missing Configuration Data: The planned order is for a configurable material, but the specific configuration (variant) has not been defined or is missing in the system.
- Incorrect Material Master Setup: The material master record for the configurable material may not be set up correctly, leading to missing configuration data.
- Incomplete BOM (Bill of Materials): The BOM for the configurable material may not include the necessary components or configurations.
- MRP Settings: The MRP settings may not be correctly configured to handle configurable materials.
Solution:
- Check Configuration Data: Ensure that the configuration data for the planned order exists. You can do this by checking the material master and the configuration profiles.
- Review Material Master: Go to the material master (transaction code MM03) and verify that the configuration settings are correctly defined for the material in question.
- Check BOM: Review the BOM for the configurable material to ensure that all necessary components and configurations are included.
- MRP Settings: Verify the MRP settings for the material to ensure that it is set up to handle configurable materials correctly.
- Create or Adjust Configuration: If the configuration is missing, you may need to create it or adjust the existing configuration to meet the requirements of the planned order.
- Re-run MRP: After making the necessary adjustments, re-run the MRP process to regenerate the planned orders and check if the error persists.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or refer to SAP community forums for additional assistance.
Get instant SAP help. Start your 7-day free trial now.
61262
Project and/or WBS element does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
61261
Project does not allow individual project production
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
61264
Missing configuration in sales requirement &1
What causes this issue? The customer requirements (sales order, delivery, etc.) for a configurable material is incorrect: No configuration valuation ...
61265
You can maintain the components by exploding the BOM
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.