Message type: E = Error
Message class: 06 -
Message number: 418
Message text: Can delivery date be met? (Realistic delivery date: &)
The date is the delivery date taking into account the
<GL:planned_delivery_time>planned delivery time</> in the
<GL:material_master_record>material master record</>
purchasing department processing time from the materials planning
Customizing facility
INCLUDE NA_T160M LANGUAGE EN
You can change the delivery date originally entered and enter the
realistic delivery date &V1&.
Error message extract from SAP system. Copyright SAP SE.
06418
- Can delivery date be met? (Realistic delivery date: &) ?The SAP error message 06418, which states "Can delivery date be met? (Realistic delivery date: &)," typically occurs during the sales order processing or delivery scheduling in SAP. This message indicates that the system is unable to confirm the requested delivery date for a sales order or delivery due to various reasons, such as material availability, production capacity, or transportation constraints.
Causes:
- Material Availability: The required materials for fulfilling the order are not available in stock or cannot be produced in time.
- Production Capacity: The production resources may be overloaded, leading to delays in manufacturing the required items.
- Transportation Issues: There may be logistical challenges that prevent timely delivery, such as transportation capacity or scheduling conflicts.
- Lead Times: The lead times defined in the system for procurement, production, or delivery may not align with the requested delivery date.
- Configuration Issues: Incorrect settings in the material master, sales order, or delivery scheduling parameters can lead to unrealistic delivery dates.
Solutions:
- Check Material Availability: Review the stock levels and availability of the materials required for the order. If materials are not available, consider placing purchase orders or adjusting production schedules.
- Adjust Production Schedules: If production capacity is an issue, evaluate the production plan and consider reallocating resources or adjusting priorities to meet the delivery date.
- Review Transportation Plans: Ensure that transportation arrangements are in place and that there are no conflicts that could delay delivery.
- Update Lead Times: Verify and, if necessary, update the lead times in the material master or sales order to reflect realistic expectations.
- Consult with Relevant Departments: Collaborate with procurement, production, and logistics teams to identify bottlenecks and develop a plan to address them.
- Use Alternative Dates: If the requested delivery date cannot be met, communicate with the customer to propose an alternative delivery date based on the realistic delivery date provided by the system.
Related Information:
By addressing the underlying causes and implementing the suggested solutions, you should be able to resolve the error message and ensure that delivery dates are realistic and achievable.
Get instant SAP help. Start your 7-day free trial now.
06417
With multiple acct. assignment, enter GR non-val. or cancel GR
What causes this issue? In the case of <DS:GLOS.3526C07CAFAB52B9E10000009B38F974>PO items assigned to more than one account</>, instead o...
06416
Please enter a percentage smaller than 100 %
What causes this issue? The percentage you entered in the account assignment item is greater than 100%.How to fix this error? INCLUDE EINGABE_PRUEFE...
06419
With multiple accounting lines, distribution indicator cannot be single
What causes this issue? The system issues an error message and will not allow you to continue with this transaction until the error is resolved. <...