Do you have any question about this error?
Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 112
Message text: Leistung aus Soll=Ist-Verrechnung darf nicht aufgenommen werden
You want to input activities from sender cost center/activity type
&V1&/&V2&.
Since you have set the Actual activity type category to Target=actual
activity allocation (category 5) in fiscal year &V3& in version &V4&,
only cost centers, cost centers/activity types, and business processes
can currently input this activity.
The entry is not accepted
Use a sender cost center/activity type with another actual activity
type category or, if possible, change the actual activity type
category.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
K8112
- Leistung aus Soll=Ist-Verrechnung darf nicht aufgenommen werden ?Get instant SAP help. Start your 7-day free trial now.
K8111
Sekundäre Kostenart & ist bei Ressourcenplanung nicht zulässig
Was verursacht dieses Problem? You want to carry out a resource planning with cost element &V1&. However, in fiscal year &V2& this...
K8110
Der Preis für Ressource & ist nicht in allen Perioden bekannt
Was verursacht dieses Problem? You want to carry out resource planning for resource &V1& on cost center &V2&. In fiscal year &V...
K8113
Leistung darf nur unter Kostenart &3 aufgenommen werden
Was verursacht dieses Problem? You want to input activities from sender cost center/activity type &V1&/&V2& under cost element for ...
K8114
Prozessmenge aus Soll=Ist-Verrechnung darf nicht aufgenommen werden
Was verursacht dieses Problem? You want to input process quantities from sender business process &V1&. Since you have set the Actual activi...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.