Message text: Auftrag & Vorgang &: Max. Übergangszeit zum Nachfolger & überschritten
You want to schedule an operation of a process order. A maximum
interoperation time or an overlap with a predecessor operation has been
defined via the relationships between the assigned phases.
The scheduling result has led to a violation of this restriction. The
reason for this was either manual planning or missing capacity at the
resource.
Please reschedule the operation manually or
reschedule a different occupancy.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CY713
- Auftrag & Vorgang &: Max. Übergangszeit zum Nachfolger & überschritten ?Get instant SAP help. Start your 7-day free trial now.
CY712
Auftrag & Vorgang &: Max. Übergangszeit zum Vorgänger & überschritten
Was verursacht dieses Problem? You want to schedule an operation of a process order. A maximum interoperation time or an overlap with a predecesso...
CY711
Auftrag & Vorgang &: Keinen Kapazitätsbedarfssatz gefunden
Was verursacht dieses Problem? No capacity requirements were generated for the operation when lead time scheduling was carried out for the order.Wi...
CY714
Auftrag & Vorgang/Phase & hat Status "rückgemeldet"
Was verursacht dieses Problem? You are trying to dispatch or reschedule an operation or a phase. However, the operation or the phase has the status...
CY715
Auftrag & Vorgang/Phase & hat Status "teilrückgemeldet"
Was verursacht dieses Problem? You are trying to dispatch or reschedule operations or phases belonging to process orders. The operations or phases ...