Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 061
Message text: Projektdefinitionen unterscheiden sich in Kopf und Vorgang
The network you are editing has account assignment.
The WBS element that you want to assign to an activity has a different
project definition than the one you have entered in the network header.
The WBS element in the activity must have the same project definition as
in the network header.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
RESET N1
Check to make sure that you entered the correct WBS element. If
necessary change your entry.
Check the project definition of the WBS element and change it if
necessary.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CN061
- Projektdefinitionen unterscheiden sich in Kopf und Vorgang ?Get instant SAP help. Start your 7-day free trial now.
CN060
Kostenanzeige konnte wegen fehlende Parameter nicht erzeugt werden
Was verursacht dieses Problem? The cost display could not be created. An internal error occurred.Systemantwort INCLUDE 'NA_ALLG_NOVERARBEITU...
CN059
Vorgang hat keine Kosten
Was verursacht dieses Problem? No planned costs could be calculated for the activity.Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE ...
CN062
& Endtermin liegt in der Vergangenheit
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CN063
Teilnetz kann nicht erstellt werden
Was verursacht dieses Problem? You have not maintained all the parameters in Customizing which are necessary to create a subnetwork.Systemantwort ...